The following schedule is subject to change due to utility and other conflicts and weather related delays. The NYC Department of Transportation will mill these streets, leave them unpaved for 1-2 weeks to allow for utility work, and repave them with fresh asphalt.

Month Street Cross Street 1 Cross Street 2
April 10 Street 3rd Avenue Prospect Park West
April 6 Avenue 15th Street 4th Street
April Warren Street 4th Avenue 5th Avenue
April Amity Street Hicks Street Court Street
April Congress Street Hicks Street Court Street
April Verandha Place Henry Street Clinton Street
April 2nd Place Henry Street Smith Street
April Luquer Street Hamilton Avenue Smith Street
April Richards Street Verona Street  Beard Street
April Sullivan Street Richards Street Ferris Street